TK Study

Software Engineering › Learn step by step › Y12 SE Project

Item 338 of 426 · Year 12: The Software Engineering Project, 10 of 47

Direct implementation

Term Key terms bank

Jump to a topic
  1. Exam format, question types and command words (46)
  2. Year 11: Programming Fundamentals (69)
  3. Year 11: The Object-Oriented Paradigm (33)
  4. Year 11: Programming Mechatronics (29)
  5. Year 12: Secure Software Architecture (57)
  6. Year 12: Programming for the Web (59)
  7. Year 12: Software Automation (35)
  8. Year 12: The Software Engineering Project (47)
  9. Diagrams and modelling tools (18)
  10. Python, SQL, pseudocode and CSS patterns (33)

See every item in the sequence

Definition

The old system stops and the new one starts straight away; cheap and fast but risky.

Example: Switch off the old system on Friday and use the new one Monday.

Found in: syllabus, 2025 HSC marking guidelines, school notes, past SDD papers.

Short version to memorise (key terms bank)

Old system off, new on at once.

Where you'll use it in the test

Syllabus area: Y12 SE Project.

Question types it can appear in

Where it has appeared in the paper

The Software Engineering Project (Part A, B). Part letters follow each paper’s own layout.

Related past questions

How to use it

A model sentence

General advice, built from the definition and example above

“The old system stops and the new one starts straight away; cheap and fast but risky.” Then apply it: Switch off the old system on Friday and use the new one Monday.

In a short answer, give the definition in your own words first, then tie it to the situation in the question. Do not copy the example above unless it fits the scenario.

Command words used with it

From the linked past questions
  • Identify: Recognise and name. (2025 HSC Q1 (1 mark): Implementation methods)

Official worked answer

Sample exam Q5 (1 mark): Implementation methods (1 mark): official criteria and sample answer

Criteria

1: Correctly matches the implementation methods.

Sample answer

(i) Direct. (ii) Phased. (iii) Parallel. (iv) Pilot.

Open the question page

Go deeper

Check yourself

Explain “Direct implementation” in one sentence, give an example, and name a question type that could test it.

Reveal the answer

The old system stops and the new one starts straight away; cheap and fast but risky.

Example: Switch off the old system on Friday and use the new one Monday.

Could be tested as: Multiple choice, Matching or table, Short answer.