Multiple choice › Implementation methods
Implementation methods
1. Implementation methods
A new system is being implemented. The old system will be kept running until all problems with the new system are resolved. Which installation method is being used?
- Pilot
- Phased
- Parallel
- Direct cut over
Answer
C
NESA answer key: C. Old syllabus (SDD): useful as overlap practice only.
2. Implementation methods
A bank installs its new system in one branch first, and rolls it out to all branches once it works well. Which implementation method is this?
- Phased
- Pilot
- Direct
- Parallel
Answer
B
Pilot = trial with a small group/location first. Phased = one module/part at a time. Parallel = old and new run together. Direct = switch immediately.
3. Implementation methods
Which implementation method carries the HIGHEST risk if the new system fails?
- Phased
- Direct cut-over
- Parallel
- Pilot
Answer
B
With direct changeover the old system is switched off immediately, so there is no fallback.
4. Implementation methods
A company replaces its old payroll software by adding one new module (such as leave) at a time over six months. Which method is this?
- Pilot
- Direct
- Parallel
- Phased
Answer
D
Phased implementation introduces the new system gradually in stages.